Genex Power has announced it has entered into a binding connection agreement with Essential Energy, responsible for one of Australia’s largest distribution networks, for the 50MW Jemalong Solar Project in New South Wales.

The connection agreement allows for the connection of the project in the National Electricity Market (NEM) via Essential Energy’s distribution network.

The connection point will be located at the existing West Jemalong 66/11kV Zone Substation, situated within close proximity to the project site, minimising construction cost and time.

The execution of the agreement means the project is now classified as a committed generator, with its position secured within the NEM.