Foundations in place at Mount Emerald Wind Farm

Construction at the $360 million Mount Emerald Wind Farm near Mareeba reached an important milestone last week when the first of 53 turbine foundations were put in place.

The 800-tonne foundation, which is buried to ground level, provides an immovable anchor for each turbine and consists of a 50-tonne reinforced steel cage filled with around 350 cubic-metre tonnes of concrete, or up to 70 truckloads.

Ratch Australia corporation executive business development general manager Anthony Yeates said the first foundation was always a special milestone in wind farm construction.

“Up until this point, the focal point for construction has been civil works, establishing the site office and constructing access roads following meticulous flora, fauna and unexploded ordinance surveys,” Mr Yeates said.

“Getting the first foundation poured is the first big ticket items on our scope of works that has to do directly with the wind turbines, so for us it’s a special moment that salutes years of hard work by many people in our team.”

The concrete used for each foundation would be manufactured onsite to reduce truck movements on public roads.

Up to four weeks is allowed for the concrete to cure to maximum strength before the foundation is backfilled with rock and soil to match the natural surface level.

At this point, the foundation is ready for the bottom section of the tower to be bolted to it.

Wind turbine components will be delivered over an eight-month period starting in October.

Each turbine will have a capacity exceeding 3MW making a total capacity of around 180MW to be connected to the electricity grid.

“It’s exciting to see the project really begin to take shape,” Mr Yeates said.

“Now that we have the foundations underway, we hope to have the first tower sections going up within the next two months, followed eventually by the installation of the nacelles and then the turbine blades.”

Once fully operational in September 2018, Mount Emerald will be the biggest wind farm in Queensland.

The wind farm is located near Edify Energy’s 150MW Daydream Solar Farm and 50MW Hayman Solar Farm, which are about to begin construction.

Previous articleSEA Electric to convert commercial vehicles to EV